MSc Aquatic Ecosystem Management |
|
|
Seafield Wastewater Treatment Works
Sewage is gathered from Edinburgh and surrounding communities (population approx 2 million) via the Interceptor sewers, which were constructed in the late 1970's to divert raw sewage from the beaches. They enter the works via a pair of siphons, and are then subjected to the first process, screening on a pair of inclined screens. This removes the "rags", objects larger than 6mm.
The design Dry Weather Flow is 261,441cubic metres per day, and the works is designed to be capable of treating 3 times this.
Above 3 x DWF, the excess is diverted into an older part of the works where additional screening can occur. This provision, and that of storm tanks, is necessary because the sewerage system is 'combined', meaning that domestic, industrial, and surface drainage all goes into the same system.Click on the images to see a larger version
| The flow is then passed to the 4 grit settlement tanks: | Flow through the tanks is slowed down by the baffles, allowing heavier particles (road grit, etc.) to settle out: |
|
| Paddles scrape the grit into the centre, from where it is lifted and transported to a washer. |
The grit
is collected, drained and sent to landfill or for land reclamation. |
|
The sewage passes from the grit separators via a set of penstocks and flow measuring flumes to the circular primary settlement tanks. |
The sewage (average BOD about 150, Total Suspended Solids about 140mg/l) is fed to the centre
of the tank and flows towards the perimeter. As
it does so its velocity decreases and the particulate material settles
out as sludge, removing 35% of the BOD and 55% TSS. |
|
| The effluent flows under a baffle designed to remove fats, and over a V-notch weir. |
The effluent is a grey, opalescent colour at this stage, and its BOD and TSS is still too high (around 100 mg/l BOD, 70 TSS) to discharge into the Forth estuary, according to the consents currently set by SEPA. |
|
| The sediment sludge is collected by airlift pumps from the bottom of the tank: these tanks are relatively shallow as the site is built on reclaimed land on the coast, and suffers from a high water-table, which means empty tanks might float. |
The gantry carrying the airlift system sweeps around the tank, skimming fats at the surface also | |
| From this point onwards there are two streams to follow: the effluent, which is eventually discharged into the Forth Estuary, and the sludge, which meets up with sludge from other processes for final treatment. When the works was first commissioned, only this primary treatment was deemed necessary: the effluent went straight out to the Forth via a long sea outfall pipe with diffusers, and the sludge was dumped at sea by a boat, poetically called the 'Gardyloo'. The sludge has its water content reduced in Picket Fence Thickeners, a form of strainer. The water from this re-joins the effluent stream. |
During storm events flow is
diverted via the penstocks and overflow weirs into the four storm tanks
(100m x 30m and 3.4 metres deep). The tanks are seen full here: the rainfall during the previous night had been prolonged but not unusual: any excess at this point would have to be spilled directly into the Forth as there is no further storage capacity, however, the sewage would be very dilute as the major part of the volume would be rainwater, and the sewers would already have been well flushed of solids. |
|
| Once the excess input has stopped, pumps at the bottom of the
tanks are switched on to resuspend the sediment. After a storm the sewage in
the tanks is pumped into the main treatment stream. |
The effluent from the primary
settlement tanks undergoes a biological treatment by the Activated Sludge
process (ASP). The effluent passes through a raceway system of deep (6.1
metre) tanks which have air blown in at the bottom, forcing oxygen into
solution. Flocs of bacteria grow aerobically, using the carbonaceous material in the sewage as an energy source and thus reducing the Biochemical Oxygen Demand (BOD). |
|
| The diffusers at the bottom of the lanes are arranged to give tapered aeration,
with more air delivered at the start of the process where it is most needed, |
while the diffusers towards the end are more spaced out. |
|
| If the BOD was not reduced
in the treatment process, oxygen would be used up in the receiving water,
resulting in anoxic conditions, killing marine organisms, and causing
the sediments to produce hydrogen sulphide. The dissolved oxygen and solids
content in the activated sludge tanks is closely monitored. The grey box on the rail houses the oxygen monitoring equipment. |
A certain proportion of the
bacterial flocs (the sludge) is returned to the start of the process to
maintain a viable number of the essential bacteria. The activated sludge
mix at the end of the process is passed to setlement tanks similar to
the primary settlement tanks for the separation of the sludge and effluent. |
|
| The design of these tanks is slightly different from the primary tanks in that it has a slightly funnel-shaped profile: this picture shows the rotating
gantry which sweeps the bottom of the tank and removes the sludge via
the well in the centre: any not required to re-join the ASP joins the
primary sludge stream. |
The secondary effluent is
much clearer than the primary, and its BOD is sufficiently low to allow
it to be discharged (BOD10, TSS15 mg/l): in fact it may be mixed with some primary effluent
which has not received the full treatment. |
|
| During winter the effluent flows straight out through the outfall tunnel,
but during the bathing season it is disinfected by being passed under a bank of UV lights. |
The effluent passes through mesh screens first to remove residual rags
which have escaped the earlier screening: these are being cleaned while the system is not in use. |
|
This problem has meant that the untreated fraction of primary effluent has had to be diverted from the UV disinfestion process and is treated by dosing with peracetic acid in an unused primary tank. |
||
These pictures show the last set of UV tubes which irradiate the 5 lanes of effluent (lamps not in use at the time).
|
This is one rack of the UV tubes, each in a quartz tube: these racks are lowered directly into the flow of effluent
|
|
| Returning to the sludge stream,
sludge may be mixed with sludge brought in from smaller sewage works,
before being pumped into the digesters. Air from parts of the sludge processing
stream are passed over calcified seaweed (maerl) to remove odours. |
The digesters contain anaerobic
bacteria which break down organic material, generating methane. This is
stored in the white sphere at the end of the row of digesters, and is
used as a source of fuel for heating the digesters, and as for generating
electricity to partially power the whole works, via a CHP plant. |
|
| The digestion reduces the
total solids content of the sludge, making it easier to dispose of. It
is relatively innocuous material at this stage, and is collected in this
tank before final processing. |
The final processes involve
removing the water: the sludge passes to a tank where it is mixed with
polymer which encourages it to clump together, and then to a belt thickener
to remove much of the water. |
|
polymer |
||
| This is a large fabric belt
which allows the liquid to pass through, while the solids are carried
to the end of the belt and dropped into a hopper. |
Views of the belt thickeners |
|
| The thickened sludge
is then passed to centrifuges where remaining water is removed. |
||
| The water from these
processes is returned to the treatment stream and undergoes primary and
secondary treatment. |
The solids from the
centrifugation were formerly discharged at this point and either taken
to landfill or used in land reclamation or forestry, uses which avoided
direct contact with forage crops. |
|
| Recently drying and pelletising equipment has been commissioned. | This further dries the sludge using heat and compresses it into pellets which are bagged and sold: it may be used as agricultural fertiliser as the process sterilises the sludge. | |
Thus the Seafield sewage works, currently operated by Thames Water, carries out primary screening, grit separation, stormwater storage and treatment, primary settlement, Activated Sludge treatment, secondary settlement, effluent disinfection, sludge digestion and dewatering, concentration, pasteurisation and pelletisation. Being sited on the coast it does not have to carry out tertiary treatment (nutrient removal).